Skip to content

Demonstration site. Blueprint Mechanical is not a real contractor. Licence number, phone numbers and address are placeholders.

MECH-01

Design-build, from the load calculation to the balancing report

One contract, one accountable party, and a document at the end of every stage. We calculate the load, select against it, design the distribution, build it in our own shop, install it, and prove it works.

At a glance

Reference
MECH-01
Typical programme
8 to 22 weeks, design through commissioning
Sector
Commercial and residential
A drafting table with rolled mechanical drawings, a scale rule, an adjustable triangle and dividers under soft north light
Every job starts on paper, and the paper is issued to you.

The load calculation is the whole argument

Almost every mechanical problem we are called to fix started as a sizing decision made without a load calculation. Rules of thumb, tonnage per square foot, and matching whatever was there before are all methods of guessing, and in a city where the air is 17 percent thinner than the assumptions behind those rules, guessing is expensive.

For residential we run ACCA Manual J, room by room, not just a whole-house block. For commercial we run a block load and then a zone-by-zone breakdown, using the ASHRAE Denver design conditions: 91 °F dry bulb and 59 °F mean coincident wet bulb at the 0.4 percent cooling condition, 1 °F at the 99.6 percent heating condition.

The report comes to you with the inputs visible: glazing area and U-value, orientation, infiltration assumption, insulation levels, internal gains and the occupancy schedule. If you disagree with an assumption, that is a productive conversation to have before the equipment is ordered.

Selection against the calculated load, corrected for 5,280 feet

ACCA Manual S is the step that gets skipped most often. It is the discipline of selecting equipment against the load you calculated, at the conditions the building will actually see, rather than against a nominal tonnage on a catalogue page.

At Denver altitude the corrections are real. Sensible capacity for a given airflow drops roughly 17 percent, so the required cfm per ton rises from about 400 to 450 or 480 actual cfm per ton. Fans generate less static pressure at reduced density and draw less brake horsepower for the same volume. Gas-fired equipment above 2,000 ft needs the manufacturer high-altitude listing, which typically means an orifice change and a derated input.

The selection sheet you receive shows the catalogue capacity, the altitude correction applied, and the resulting capacity at your design condition. Three numbers, so the correction can be checked.

Distribution designed to a friction rate, not a habit

The friction rate is not 0.10 in. w.c. per 100 ft because that is the number everybody uses. It is derived: take the equipment external static pressure rating, subtract the coil, filter, and accessory losses, and divide the remainder by the total effective length of the worst run.

On a residential air handler rated at 0.5 in. w.c. with a four-inch MERV 13 filter and a wet coil, the available static pressure for the duct is often closer to 0.25 in. w.c., which gives a very different friction rate and a very different set of duct sizes. Designing to 0.10 anyway is how a new system ends up measuring 1.1 in. w.c. and delivering 70 percent of rated airflow.

For hydronic we do the same thing with head, pump curves and the actual operating point rather than the nameplate one.

Commissioning is a line item, on purpose

Commissioning and TAB appear as their own line on our proposals because they are their own work, and because a separate line is harder to quietly delete during value engineering.

Testing, adjusting and balancing means every terminal gets measured against its design airflow, dampers and valves get adjusted until they match, and the results get written down. Commissioning means the sequences of operation get verified against the written sequence, point by point, with someone signing that they did it.

You receive both reports. Where a terminal is out of tolerance, the report says so and says what was done. A system that was designed and installed correctly still does not perform correctly until it has been balanced.

Why altitude keeps appearing on this page

Because it is the single most common thing missing from the proposals our clients show us. A design that ignores 5,280 ft is not slightly optimistic, it is systematically wrong in one direction: too little airflow, too little sensible capacity, and gas equipment running outside its listing.

Questions we get about this.

If yours is not here, ask it directly. You get an answer from the engineer who would run the job, not from a call centre.

All questions
Why does altitude change how equipment gets sized in Denver?

Air at 5,280 ft is about 17 percent less dense than air at sea level. Everything that moves air or burns gas notices.

The sensible heat equation is the clearest example. At sea level it is Q = 1.08 x cfm x delta T. In Denver the constant drops to roughly 0.90, so the same air handler moving the same cfm removes about 17 percent less sensible heat. Fans also generate less static pressure at reduced density, and gas equipment above 2,000 ft needs a high-altitude orifice kit and a derated input.

A catalogue selection made on sea level data is therefore optimistic on capacity and wrong on airflow. Every selection we make is corrected for site elevation, and the correction is shown on the selection sheet.

Do you really run a Manual J on every house, or is that a sales line?

Every house, and you get the report. It lists the inputs we used: orientation, glazing area and U-value, infiltration assumption, insulation levels, and the design conditions.

The reason is not paperwork for its own sake. Oversized equipment short cycles, never reaches steady state, dehumidifies badly and wears its compressor out early. In a Denver retrofit the honest load is very often 20 to 35 percent below the equipment that is currently sitting there.

If you disagree with an assumption in the report, that is a useful conversation to have before the equipment is ordered rather than after.

What is TAB, and why is it a separate line on your proposal?

TAB is testing, adjusting and balancing. Airflows and water flows are measured against the design, dampers and valves are adjusted until they match, and the results are recorded.

It is a separate line because it is separate work, and because listing it separately makes it harder to quietly delete. A system that was designed correctly and installed correctly still does not perform correctly until it has been balanced.

You get a TAB report with the design value and the measured value side by side for every terminal. Where a terminal is out of tolerance, the report says so and says what was done about it.

Related work

Ask us about design-build.

Send us the building, the equipment and the complaint. You get a written response with the load we would run, what we would measure first, and a range before anyone visits.

Or call (303) 555-0148. Mon to Fri 07:00 to 17:00.